Need some experienced eyes on a Xcel Energy billing issue. The Schedule LPS rate schedule clearly states power factor minimum 0.95, but the bill shows no PF adjustment shown. The meter nameplate shows 400:5 but the billing system has 300:5.
car dealership account with Dominion Energy — fuel adjustment error question
Good work Linda P. For the folks following along, this is a textbook example of why we check tax exemptions on every audit.
Be careful with Louisville Gas & Electric''s refund process — they sometimes try to limit the lookback period to 2 years.
Great catch, Marilyn D. I''ve seen ConEd do this before — it''s a systemic issue in their billing system.
Wendell T, you should also check the meter configuration while you''re at it. These errors tend to cluster.